CSX Intermodal, Inc.
Little Ferry Terminal
North Bergen, NJ |
|
|
End Use
|
Railroad / Trucking Terminal |
|
Client
|
CSX |
|
Architect
|
Green & Marks, PE |
|
Perspective
|
A terminal expansion and upgrade was completed to accommodate increased traffic using this busy intermodal facility.
The driveway was expanded to allow four lanes of traffic. Inbound and outbound communication talk-back stations were installed, including kiosks and a four-lane inspection canopy. Additional track crossings and storm sewer catch basins were installed. A majority of the facility was repaved and striped. In order to accommodate for additional rail cars, abandoned tracks were brought back into service and working tracks were either repaired, removed or relocated.
|
|
Features
|
The addition of traffic lanes, new paving, yard lighting, talk-back stations, security cameras and inspection canopy will make it possible for this facility to operate more smoothly and enable the owner to track shipments with greater speed and accuracy. |
|
|
|
 |
|
|
 |
|
|
|
 |
|
 |
|
 |
|
 |
|
 |
|
 |
|
 |
|
 |
|
 |
|
|
 |
|
Hosted by:
Macmagicians.com |
|
|
|
 |
|
|
 |
|
|
|
Post construction site photo showing new four-lane canopy
|
|
|
|
Installing concrete slab on grade for new inspection canopy
|
|
|
 |
|
|
 |
|
|
|
Relocation and installation of new rail
|
|
|
|
Placing communication conduits and concrete junction boxes
|
|
|
 |
|
 |
|
|
|
Construction of additional parking areas
|
|
|
|
New rail construction
|
|
|
|
|
 |
|
 |
|
|
Installation of new storm sewer precast concrete pipe
|
|
|
|
In order to comply with local fire code regulations, the water main was expanded and new fire hydrants were installed throughout the terminal
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|